Topic: Tripp-Lite Smart UPS troubleshooting
|
|
|
|
|
|
|
|
|
Steve Guttag
We forgot the crackers Gromit!!!

Posts: 12814
From: Annapolis, MD
Registered: Dec 1999
|
posted 04-16-2018 04:28 PM
What we've strived to reduce/eliminate are single point of failures. To that end, the transfer switch to the UPS. The UPS was put in to protect the sensitive gear. In the event of a power failure or even a mere brown out, the automation pauses the show since the server and projector electronics will be unaware of the power interruption. However, when the first UPS was the cause of the failure, we had to do either come up with a transfer switch or consider eliminating the UPS.
The thing is, the UPS has been doing its job. We have lost a very low number of everything. We normally use the zero-transfer type double conversion UPSes (more than the $400 type Sam was just mentioning) so the sensitive equipment is separated from the power by a bit.
From a support standpoint, being able to remotely power the projector and server was essentially a necessity (ever tried to update a Christie? Often you have to power cycle twice!). So we added a transfer switch in there at the same time and have yet to lose a show as a result.
As we start to design implement QSYS systems in complexes, again, the question is...UPSes? Transfer Switches? UPSes have already shown themselves to be liabilities while being life-savers at the same time. So I'm thinking that putting them in as a set almost has to be a given if you don't want your backup being the cause of the problem. It is too bad that the UPS companies can't put the transfer switch in their UPS (when the unit fails, it switches back City Power. Note, there are some MANUAL transfer switches where the end user will get an LED indication of which source has power and one can select that...but again, that would require a show going down. At the heat of it, a transfer switch is nothing more than a double throw relay that can handle the current on both sets of contacts (watch out, some have drastically lower current capabilities on the NC side).
| IP: Logged
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
All times are Central (GMT -6:00)
|
This topic comprises 3 pages: 1 2 3
|
Powered by Infopop Corporation
UBB.classicTM
6.3.1.2
The Film-Tech Forums are designed for various members related to the cinema industry to express their opinions, viewpoints and testimonials on various products, services and events based upon speculation, personal knowledge and factual information through use, therefore all views represented here allow no liability upon the publishers of this web site and the owners of said views assume no liability for any ill will resulting from these postings. The posts made here are for educational as well as entertainment purposes and as such anyone viewing this portion of the website must accept these views as statements of the author of that opinion
and agrees to release the authors from any and all liability.
|